What the EU MDR delay due to the Coronavirus pandemic means for you
May 14, 2020
Need a Honeywell Account?
Already have a Honeywell account?
Sign InYou can set your preferred currency for this account.
Changing Currency will cause your current cart to be deleted. Click OK to proceed.
To Keep your current cart, click CLOSE and then save your cart before changing currency.
Switching accounts will update the product catalog available to you. When switching accounts, your current cart will not move to the new account you select. Your current cart will be available if you log back into this account again.
| Account# | Account Name | City | Zip/Post Code |
|---|
You are browsing the product catalog for
You are viewing the overview and resources for
to view parts associated with your account
May 14, 2020
The new EU Medical Device Regulation was pushed back a year. What do you do? We interviewed Sparta Systems project managers for their perspectives.
Q: As of April 2020, EU MDR has been delayed by a year. What does that mean?
A: In light of the COVID-19 pandemic, the European Commission has approved a 1-year delay in the implementation and enforcement of the new European Union Medical Device Regulation.
Q: What new requirements were captured in the EU MDR? Have there been any changes other than the delay?
A: The purpose was to update and tighten regulation of medical devices in the EU. There have been no changes to the MDR as a whole except the Date of Application delay.
Q: Why would the novel coronavirus pandemic have an effect on this regulation rollout?
A: The COVID-19 outbreak and the impact that the resulting response is having several effects that impact this change in timing of the regulation.
Q: Is the delay for Date of Application (DoA) the only change that impacted MDR project at my site, or is the impact more substantial?
A: The delay was implemented, but COVID-19 impacted MDR projects in other ways as well:
Q: What is important to know about managing current processes that are disrupted?
A: Imperatively, knowledge needs to be preserved. If a project is disrupted but expected to be revived, documenting current state while hibernating the project is critical. Critical data around open tasks and project risks need to be captured and recorded. Include timeline projections for when the situation has passed to aid in resource allocation and optimal manufacturing output.
During the pause or disruption, actively monitor the situation externally to determine the resumption timeline. Factors to consider include resource availability, onboarding, ramp up, and changes in teams.
Q: When the process is revived, how should we work smart through it?
When the workflow is opened back up again, that effort of knowledge capture will smooth the transition. Start with a re-discovery to re-assess scope, resources, and risks and determine or confirm deliverables. Do not assume conditions are the same as before a hibernation period.
No matter where you are in your quality management digital journey, Honeywell has solutions for you
Copyright © 2026 Honeywell International Inc
Due to inactivity you will be logged out in 000 seconds.
You cannot access this page as this product is not available in your country.
This product is not available in your country.
You cannot access this page as this product is not available in your current country. To view this product, please change your product catalog view.
We use cookies and similar tracking online technologies to improve website performance, record website activities, facilitate information sharing on social media and offer advertising tailored to your interest. For more information, see our Cookie Notice and Terms and Conditions. You can also customize your browser’s cookie settings. Please note that if you refuse cookies, it may affect site functionality and performance.